1、用户应根据我公司供给的根底材料图,进行混凝土根底施工。根底的装置面,应包管在同一水平面上,酸雾洗涤塔底脚须知螺栓或沓接固定在根底的钢板上。
1. The user shall carry out concrete foundation construction according to the foundation material drawing provided by our company. The device surface of the root bottom shall be guaranteed to be on the same horizontal surface, and the bottom foot of the acid mist washing tower shall be fixed on the steel plate at the root bottom with bolts or taps.


2、风机装置时,应谨防杂物掉入风机内。酸雾洗涤塔装置完成后,在试车之前有必要铲除塔内污物。
2. When the fan is installed, the sundries shall be prevented from falling into the fan. After the completion of acid mist scrubber, it is necessary to remove the dirt in the tower before commissioning.
3、因通常玻璃钢制品易燃,装置及修理过程中,禁止运用明火。
3. Since FRP products are usually inflammable, it is forbidden to use open fire in the process of device and repair.
4、如风机装置在室内,风机的电机有必要采纳防雨办法。
4. If the fan is installed indoors, it is necessary to adopt rainproof measures for the motor of the fan.
5、 酸雾洗涤塔有必要有专人职责办理,常常查看风机工作能否正常,液位能否政党液位箱中浮球开关能否正常,溶液浓度能否在规则规模等等,如发现问题,应及时处置。
5. It is necessary to assign a special person to handle the acid mist scrubber, often check whether the fan can work normally, whether the liquid level can be normal or not, whether the float switch in the liquid level tank can be normal, whether the solution concentration can be in the regular scale, etc. if any problem is found, it should be dealt with in time.
6、为保证贮液箱中液位,避免开关风机时导致液位升降,有必要在敞开风机后,敞开浮球供水阀,封闭风机前,先封闭浮球供水阀。液位高度静态应控制在离地650mm左右为宜。
6. In order to ensure the liquid level in the liquid storage tank and avoid the rise and fall of the liquid level when the fan is switched on and off, it is necessary to open the floating ball water supply valve after the fan is turned on, and close the floating ball water supply valve before the fan is closed. The height of liquid level should be controlled about 650mm above the ground statically.
7、酸雾洗涤塔金属支架至少每年进行防腐处置二次
7. The metal support of acid mist scrubber shall be subject to anti-corrosion treatment at least twice a year
酸雾净化塔操作规程 | 酸雾净化塔的工作原理
Code of operation for acid mist purification tower working principle of acid mist purification tower
1、 酸雾洗涤塔宜安装在高出地面100mm以上的混凝土基础上,水泵、风机应按要求另作混凝土基础。
1. The acid mist scrubber should be installed on the concrete foundation 100mm above the ground, and the water pump and fan should be used as the concrete foundation separately as required.
2、运输安装时要注意保护,不得碰损机体及部件。
2. Pay attention to protection during transportation and installation, and do not damage the body and components.
3、吸收塔出厂时,本厂根据具体情况,采用分段包装运输,由本厂派员到现场安装调试。
3. When the absorption tower is delivered from the factory, the factory will transport it in sections according to the specific conditions, and send personnel to the site for installation and commissioning.
4、吸收塔安装和工作在室外的,冬季应对底部水池部位注意防冻。
4. If the absorption tower is installed and operated outdoors, pay attention to antifreeze at the bottom pool in winter.
酸雾净化塔具有哪些显著的***点
What are the remarkable characteristics of acid mist purification tower
5、吸收塔底部水池有液位标记,使用前务必按液位标记注入吸收液。使用过程中应注意补充吸收液。
5. The water tank at the bottom of the absorption tower is provided with a liquid level mark, and the absorption liquid must be filled according to the liquid level mark before use. Pay attention to supplement the absorption liquid during use.
6、使用时应先开循环水泵2~3分钟,再开鼓风机,停机时,应先停鼓风机1~2分钟后,再停循环水泵。
6. The circulating water pump shall be turned on for 2-3 minutes before the blower is turned on. When the blower is turned off, the blower shall be turned off for 1-2 minutes before the circulating water pump is turned off.
7、应根据使用情况定期检查塔底部水池内液体酸性浓度及排出气口气体净化程度,超出标准时,应更换底部水池中的吸收液。
7. The acid concentration of the liquid in the tank at the bottom of the tower and the purification degree of the gas at the outlet shall be checked regularly according to the service conditions. If it exceeds the standard, the absorption liquid in the tank at the bottom shall be replaced.
8、吸收塔一年半至二年应做一次检修,检查盘状喷淋管和填料的填塞情况,并对其进行清洗。
8. The absorption tower shall be overhauled once a year and a half to two years, and the filling condition of disc spray pipe and packing shall be checked and cleaned.